The Trust are working towards the construction of business units in Crossapol.  To keep up to date on this project and for more information, see our latest updates below. 

 

October Update

1 October 2023

As anyone who has passed through Crossapol lately will have seen, the last months have seen huge progress in the construction of the four new light commercial units being built under our subsidiary Tiree Community Enterprise Ltd. 

Local contractor John MacKinnon Builders Ltd completed the foundation slab work in early September, and assembly of the timber frame kits has quickly followed. Work has also progressed on the pad for the new transformer which SSEN will be installing to provide electricity supply to the site. We are still targeting a February 2024 completion date for the project

Following advertising for expressions of interest and then an application process, the provisional allocation of the units to prospective tenants has now been completed.

We would like to thank the volunteer representatives from other community groups that kindly took part in the panel, alongside members of the Business Units working group, to oversee the robust and fair process of allocation. 

The official announcement of who will be occupying the units once completed will be made in due course once we reach the point of signing leases – but there are exciting developments to come

Business Units Allocations

No Comments

Tiree Community Enterprise Ltd. (TCEL) will construct 4 light commercial business units in Crossapol, on a site directly west of the Island Centre. All units will have three phase power supply. Due to the high level of interest in the units, TCEL will conduct a formal allocations process to determine which interested parties will be allocated a business unit. This applications process is now open. The deadline for all application is 5pm Thursday 15th June.…

Read More »

Business Units – Invitation to Tender

No Comments

We are now at the stage of compiling a tender list for the construction of the business units at Crosspol. The 180m² building will consist of 4 business units in a single structure.  Tiree Community Development Trust are seeking expressions of interest from construction companies to be included in the tender list. Full tender documents will be issued in mid-late January and we aim to commence construction in mid 2023.  For further information, please contact…

Read More »

Crossapol Business Units Project Update

No Comments

We’ve now submitted a planning application for the Crossapol Business Units. You can see details of the design in the documents below.  The community’s support for this project is really important to us, therefore we are holding a Community Open Day on Tuesday 22nd November from 3pm – 7pm, at the Island Centre.  We welcome all members of the community to come along, hear more about the project and ask any questions you may have…